![](https://www.napocor.gov.ph/wp-content/uploads/Operations/Dams_Management/Dam_Sites/Mindanao/AgusVII_HEP.jpg)
History | |
Start of Construction Unit No. 1 Unit No. 2 | January 16, 1979 January 16, 1979 |
Date of Commercial Operation Unit No. 1 Unit No. 2 | March 05, 1983 December 17, 1983 |
Common Facilities | |
Basic Data Drainage Area Type | 1,883 kmĀ² Run-of-River |
Dam Type Length Crest Elevation | Concrete Gravity 173.6 m divided into 14 blocks with spillway gates centrally located at block no.7 and 10, two power intake gates at block no.5 37.5 m a.s.l. |
![](https://www.napocor.gov.ph/wp-content/uploads/Operations/Backarrow.png)