History
Start of Construction
               Unit No.1
               Unit No.2
               Unit No.3
               Unit No.4
               Unit No.5

August 1950
January 1955
July 1967
January 1970
1973
Date of Commercial Operation
               Unit No.1
               Unit No.2
               Unit No.3
               Unit No.4
               Unit No.5

July 01, 1953
November 09, 1956
July 18, 1969
April 13, 1971
April 28, 1971
Type of Plant/UnitRun-of-river
Features (Common facilities)
Dam 
TypeHybrid (Clay and Concrete Retaining Wall with Rockfill Outer Shell)
Height12.5 m
Top Width8.95 m
Crest Elevation197.0 M.S.L.
Length along Crest of Dam67.0 m
Base Width of Max. Section36.0